TOKYO, Japan, March 14, 2011 — Renesas Electronics Corporation (TSE: 6723) has announced the impact of the earthquake in northern Japan on March 11, on Renesas Electronics Group (“the Group”) and its response to the blackout measure announced by Tokyo Electric Power Company.

Renesas Electronics intends to add details of the impact from the earthquake to its financials when confirmed information is available.

(1) Status of the Group's manufacturing sites

The Group has confirmed that seven out of 22 of its factories in Japan have temporarily shut down production. Among these factories, Renesas Yamagata Semiconductor Tsuruoka Factory is currently beginning its startup procedures to restart its manufacturing. The Group is assessing the extent of the status of the remaining six factories.

[Renesas Electronics Group's factories that are currently shutting production due to the earthquake (as of March 14, 2011, 12:00 p.m.)]

 FactoryCity/Prefecture
1Renesas Northern Japan Semiconductor, Inc., Tsugaru Factory (Front-end line)Goshogawara-shi, Aomori
2Renesas Yamagata Semiconductor Co., Ltd., Tsuruoka Factory (Front-end line)Tsuruoka-shi, Yamagata
3Renesas Electronics, Naka Factory (Front-end line)Hitachinaka-shi, Ibaragi
4Renesas Electronics, Takasaki Factory (Front-end line)Takasaki-shi, Gunma
5Renesas Electronics, Kofu Factory (Front-end line)Kai-shi, Yamanashi
6Renesas High Components, Inc. (Back-end line)Tsuruta-cho, Aomori
7Renesas Northern Japan Semiconductor, Inc., Yonezawa Factory (Back-end line)Yonezawa-shi, Yamagata

(2) Response to the blackout measure

The Renesas Electronics Group's offices that will be impacted from the blackout measure announced by Tokyo Electric Power Company on March 13 are as follows:

[The Group's offices that will be impacted from the blackout measure and their countermeasure taken on March 14 and 15]

Office/SiteCity/PrefectureCountermeasure taken on March 14Countermeasure taken on March 15
1Renesas Electronics, Tamagawa Office (R&D site)Kawasaki-shi, KanagawaClosed during afternoonOpen (Note)
2Renesas Electronics, Musashi Office (R&D site)Kodaira-shi, TokyoClosed during afternoonClosed
3Renesas Electronics, Sagamihara Office (R&D site)Sagamihara-shi, KanagawaClosedClosed
4Renesas Electronics, Takasaki Factory (Front-end line)Takasaki-shi, GunmaClosed during afternoonClosed
5Renesas Electronics, Naka Factory (Front-end line)Hitachinaka-shi, IbaragiClosedClosed
6Renesas Electronics, Kofu Factory (Front-end line)Kai-shi, YamanashiClosedClosed
7Renesas Micro Systems Co., Ltd. (R&D site)Yokohama-shi, KanagawaClosed during afternoonOpen (Note)
8Renesas Eastern Japan Semiconductor, Inc., Tokyo Device Division (Back-end line)Oume-shi, TokyoClosed during afternoonClosed

(Note) Employees able to commute will work at the office.