Skip to main content

UPDATE 3- Regarding the Impact of the March 11 Earthquake on Renesas Electronics Operations and Its Response to the Blackouts

March 16, 2011

TOKYO, Japan, March 16, 2011 — Renesas Electronics Corporation (TSE: 6723) has announced the impact of the earthquake in northern Japan on March 11, on Renesas Electronics Group (“the Group”) manufacturing sites and its response to the planned blackouts implemented by Tokyo Electric Power Company and Tohoku Electric Power Company. The Group intends to add details of the impact from the earthquake to its financials when confirmed information is available.

As of March 16, 12:00p.m., following seven factories out of 22 of the Group's factories in Japan have been temporarily shutting their production.

[Status of Renesas Electronics Group's factories (as of March 16, 2011, 12:00 p.m)]

FactoryCity/ PrefectureBuildingManufacturing EquipmentOperational Status and Status of Electric Power SupplyStatus of the investigation
1Renesas Northern Japan Semiconductor, Inc., Tsugaru Factory (Front-end line)Goshogawara-shi, AomoriPartial damage confirmedCurrently assessing the statusCurrently assessing the status, Remain without electricityAssessment of manufacturing equipment to begin after electricity is restored
2Renesas Yamagata Semiconductor Co., Ltd., Tsuruoka Factory (Front-end line)Tsuruoka-shi, YamagataNo damage confirmedNo damage confirmedHalting startup procedure temporarily, Subject to the planned blackoutPreparing to halt the startup procedure temporarily in response to the planned blackout
3Renesas Electronics Corporation, Naka Factory (Front-end line)Hitachinaka-shi, IbarakiDefect identified (Assessing the extent of the damage)Defect identified (Assessing the extent of the damage)Temporarily shutting production, Remain without electricity.Plan to assess the status of inside the clean room after electricity is restored
4Renesas Electronics Corporation, Takasaki Factory (Front-end line)Takasaki-shi, GunmaPartial damage confirmedNo damage confirmedPreparing to begin startup procedures to restart its manufacturing, Subject to the planned blackoutPlan to begin startup procedures to restart its manufacturing after the planned
5Renesas Electronics Corporation, Kofu Factory (Front-end line)Kai-shi, YamanashiPartial damage confirmedPartial damage confirmedPreparing to begin startup procedures to restart its manufacturing, Subject to the planned blackoutPlan to begin startup procedures to restart its manufacturing after the planned blackout is terminated
6Renesas High Components, Inc. (Back-end line)Tsuruta-cho, AomoriNo damage confirmedNo damage confirmedPreparing to begin startup procedures to restart its manufacturing, Subject to the planned blackoutPlan to begin startup procedures to restart its manufacturing after the planned blackout is terminated
7Renesas Northern Japan Semiconductor, Inc., Yonezawa Factory (Back-end line)Yonezawa-shi, YamagataPartial damage confirmedPartial damage confirmedBegan startup procedures to restart its manufacturing, Subject to the planned blackoutProceed with the startup procedures to restart its manufacturing when the planned blackout is not implemented
8Renesas Eastern Japan Semiconductor, Tokyo Device Division (Back-end line)Oume-shi, TokyoNo damage confirmedNo damage confirmedRestarted part of its manufacturingRestarted its manufacturing during the time when the planned blackout is not implemented, however, only for those products that had been in progress

The content in the press release, including, but not limited to, product prices and specifications, is based on the information as of the date indicated on the document, but may be subject to change without prior notice.